ESB lands located to the south of the existing Ringsend 110kV Substation on the Poolbeg Peninsula,, Southbank Road, Ringsend, Dublin 4

May 30 2024

Application Received

Jul 24 2024

Decision

Jul 24 2024

Decision Due

Jul 24 2024

Granted

Jul 22 2026

Commencement Notice

Jul 31 2026

Commencement Started
  • Submitted: 30 / 05 / 2024
  • Application Type:
    Permission
  • Application Status:
    Decision Notice Issued
  • Council Decision:
    GRANT PERMISSION (Granted)

Useful Links:

Development Description:

PERMISSION for development at this c 2.4 ha site on ESB lands located to the south of the existing Ringsend 110 kV Substation on the Poolbeg Peninsula, Southbank Road, Ringsend, Dublin 4. The development will consist of the removal of the existing Air Insulated Switchgear (AIS) electrical substation and the construction of a new 110 kV Gas Insulated Switchgear (GIS) electrical substation and will include the following elements: a. Construction of a new substation compound of approximately 3916 m², with a c. 2.6 m high palisade fence around the entire perimeter of the substation. The compound comprises a new indoor 20 bay GIS building measuring c. 1,090 sq.m (c. 44.5 (m) x c. 24.5 (m) x c. 16.3 (m); b. Provision of new electrical plant and equipment within the substation including: -2 no. Transformer bunds (Length (c. 22.9m) x Width (c. 10.9m) x Height (c. 7.0m)); -2 no. 110 kV electrical transformers and associated outdoor electrical equipment to facilitate underground cable connections between the existing transmission circuits and the proposed GIS building: c. Provision of site services including compound lighting, telecommunications, access roads and drainage; d. Subsurface ground surface water attenuation tank (c. 143 m2 ); e. All associated and ancillary site development works to accommodate the construction of the substation and transferring of the cable circuits from the existing AIS to the new GIS Building; and f. Retirement and removal of the above ground elements associated with the existing AIS. The application is partially located within Poolbeg West Strategic Development Zone (SDZ) Planning Scheme area. Planning permission is being sought for a period of 10 years. The application includes a Natura Impact Statement (NIS).

Nearby Applications:

Appeals / Commencement

No Appeals Found

Decision Appealed:

  • Appeal Submitted:
  • Appeal Status:
  • Appeal Decision:
  • An Coimisiún Pleanála File Ref.:
  • Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.

No Commencement Found

Commencement Information:

  • Notice Submitted: 22 / 07 / 2026
  • Start Date: 31 / 07 / 2026
  • BCMS Notice: Subscriber Access Required