Coolcor , Rhode , Co. Offaly
Jun 10 2025
Further Info. RequestedAug 06 2025
Further Info. ReceivedSep 02 2025
DecisionSep 02 2025
Decision DueOct 08 2025
GrantedMar 30 2026
Commencement NoticeApr 06 2026
Commencement StartedOct 07 2030
Expiry (if required)-
Submitted: 17 / 04 / 2025
-
Application Type:
PERMISSION -
Application Status:
APPLICATION FINALISED -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
an Operations Building with a floor area of approximately 285m2. The Operations Building will consist of:
- 1 No. Kitchen/Mess
- 1 No. Locker Room including welfare facilities
- 1 No. Accessible Toilet
- 1 No. Toilet
- 3 No. Offices
- 1 No. Workshop/Store
- 2 No. Server/IT store
- 1 No. Meeting room
- 1 No. External compound
- 6 No. Permanent storage containers
- Roof mounted solar panels
- Connection to existing water, storm water and sewage infrastructure at Rhode Green Energy Park
- Temporary cabins to be used during the construction phase
- External parking, EV charging, lighting, CCTV, fencing etc. and ancillary site works
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision:
- An Coimisiún Pleanála File Ref.:
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted: 30 / 03 / 2026
- Start Date: 06 / 04 / 2026
- BCMS Notice: Subscriber Access Required
- View on BCMS Website
Copyright:
Planning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.