Inchacooly Ullard (Controversyland) Clonanny Kilmullen Derrynafunshion Ballycarroll (Jamestown Electoral Division) Closeland or Cloneen Ballybrittas Emo Park Cappakeel Morett Killone Garryduff (Kilmurry Electoral Division) , Killenny (Kilmurry Electo
May 15 2025
Further Info. RequestedAug 07 2025
Further Info. ReceivedSep 30 2025
DecisionOct 01 2025
Decision DueOct 29 2025
Appeal SubmittedFeb 25 2026
Appeal DecisionFeb 24 2031
Expiry (if required)-
Submitted: 24 / 03 / 2025
-
Application Type:
PERMISSION -
Application Status:
APPLICATION FINALISED -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
for works associated with the proposed uprate of the existing 110 kV Overhead Line (OHL) between the existing Cushaling 110 kV substation in the townland of Ballykilleen, Co. Offaly & the existing Portlaoise 110 kV substation in the townlands of Clonminam & Kylekiproe, Co. Laois. The replacement (“restringing”) of the existing overhead line circuit conductor with a new higher capacity conductor incl. installation of a new fibre communication connection;
Replacement of 8 no. steel towers & their foundations; Replacement of steel members at 1 no. tower; Full tower painting required at 3 no. locations; Shear block remedial works (raise & cap) at 6 no. tower locations; Replacement of wooden poles only at 15 no. locations; Replacement of wooden poles & crossarm at 5 no. locations; Replacement of crossarm only at 14 no. locations; Replacement of existing danger notices at various locations, as required; Replacement of hardware and fittings, such as insulators, insulator hardware, earthwire hardware and anti-climbing guards at various locations as required; Replacement of suspension clamps, vibrations dampers and compression assemblies at all locations as required; All associates temporary site development works to gain access to the existing structures including clearance of vegetation, disassembly & reassembly of gate posts/piers & removal & re instatement of existing fencing; other temporary associated & ancillary development works required for the purpose of the existing circuit, including temporary items, such as; guard poles, construction compounds (located in the townlands of Bracklone, Tullaghan, Morett, Clonaddodoran and Kyletalesha), clearance or management of vegetation, installation of silt traps, silt fences, stone tracks, ground protections mats & watercourse crossings.
No additional structures are proposed along the existing circuit. Structure 203,which will be relocated approx. 101m back towards structure 202 due to its existing position on top of a gravel mound & there being potential for subsidence of the gravel in the long term. No alteration to the nature, extent, alignment, character, or voltage of the existing electricity infrastructure is proposed. In addition, works to support this uprate also include the Cushlaing-Portlaoise 110KV bay lead-in conductor uprate at the Portlaoise 110KV station. A Natura Impact Statement (NIS) has been submitted with this application. Full description of all works within Site Notice.
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision: CONDITIONAL
- An Coimisiún Pleanála File Ref.: 500151
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted:
- Start Date:
- BCMS Notice:
- View on BCMS Website
Copyright:
Planning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.