Milebush Quarry, Ballynabointra and Burgesland, Midleton, Co. Cork, P25 NV27
Nov 11 2026
Decision Due-
Submitted: 17 / 09 / 2026
-
Application Type:
Permission -
Application Status:
Awaiting Technical Validation -
Council Decision:
N/A (Unknown)
Useful Links:
Development Description:
the backfilling of an exhausted quarry void (quarry registration ref: QR078) and acceptance, short-term storage
and processing of construction and demolition (C&D) waste on-site, within an overall application area of circa
(ca). 11.2 hectare (ha.). The development will consist of the backfilling of the quarry void (ca. 4.9ha) to a level of
ca. 27 metres above Ordnance Datum (mAOD) with either:
1) Inert soil and stone waste (imported inert greenfield and non-greenfield soils and stones, and river dredge
spoil which will result in the proposed development operating as a soil recovery facility that requires a waste
management licence from the Environmental Protection Agency (EPA); or
2) Soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be
notified to the EPA as an Article 27 by-product at its source of origin and transported as a by-product
material to enable the site to be backfilled.
The proposed C&D processing facility will cover an area of ca. 1.9ha and will operate under a waste
management licence from the EPA. The development will also comprise of the construction of an inspection shed
(ca.140m2) and ancillary improvements to drainage and landscaping. The development will utilise existing
infrastructure on-site including weighbridge, wheelwash, garage, car parking and welfare facilities. The
development will also include junction improvement works at the L7648 / N25 junction, located ca. 120m north
of the quarry entrance. The application relates to development which involves an activity requiring a waste
licence from the EPA.
A planning permission of 20 years is being sought for the proposed development. An Environmental Impact
Assessment Report (EIAR) and a Natura Impact Statement (NIS) will be submitted to the Planning Authority
with the application. The planning application, Environmental Impact Assessment Report (EIAR) and Natura
Impact Statement (NIS) may be inspected or purchased at a fee not exceeding the reasonable cost of making a
copy at the offices of the Planning Authority, County Hall, Carrigrohane Road, Cork, during its public opening
hours of 9.00am to 4.00pm, Monday to Friday (excluding public holidays). A submission or observation in
relation to the application, EIAR and/or NIS may be made in writing to the Planning Authority on payment of
the prescribed fee within the period of 5 weeks beginning on the date of receipt by the Authority of the
application, and such submissions and observations will be considered by the planning authority in making a
decision on the application. The planning authority may grant permission subject to or without conditions or
may refuse to grant permission.
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision:
- An Coimisiún Pleanála File Ref.:
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted:
- Start Date:
- BCMS Notice:
- View on BCMS Website
Copyright:
Planning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.