FINCASHEL , PETTIGO , DONEGAL PO
Apr 17 2025
DecisionApr 23 2025
Decision DueMay 21 2025
GrantedMay 28 2026
Commencement NoticeJun 12 2026
Commencement StartedMay 20 2030
Expiry (if required)-
Submitted: 27 / 02 / 2025
-
Application Type:
PERMISSION -
Application Status:
APPLICATION FINALISED -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
CONSTRUCTION OF A LIGHT ENGINEERING WORKSHOP FOR THE FABRICATION, ASSEMBLY AND MAINTENANCE OF EQUIPMENT AND VEHICLES WITH ASSOCIATED SITEWORKS, INCLUDING SITE PARKING, VARIOUS DRAINAGE SYSTEMS, NEW PROPRIETARY WASTEWATER TREATMENT SYSTEM AND ANCILLARY PERCOLATION AREA, RAINWATER HARVESTING TANK, FIREFIGHTING WATER RESERVOIR TANK, LANDSCAPING, BOUNDARY FENCE AND THE PROVISION AND DIVERSION OF EXISTING SERVICES, INCLUDING AN OVERHEAD ELECTRICITY CABLE AND ALL ANCILLARY WORKS
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision:
- An Coimisiún Pleanála File Ref.:
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted: 28 / 05 / 2026
- Start Date: 12 / 06 / 2026
- BCMS Notice: Subscriber Access Required
- View on BCMS Website
Copyright: