ESB's Enniscrone 38kV Substation (opposite frankford Close) , Enniscrone , Co. Sligo
Jul 11 2019
DecisionJul 22 2019
Decision DueAug 02 2019
Appeal SubmittedAug 26 2019
Appeal DecisionOct 10 2019
GrantedOct 09 2024
Expiry (if required)-
Submitted: 28 / 05 / 2019
-
Application Type:
PERMISSION -
Application Status:
APPLICATION FINALISED -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
Development consisting of the construction of a 20 metre high telecommunications monopole structure including antennae, dishes and associated ground-mounted equipment cabinets, all within a 2.4 m high palisade fence compound.
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision: REFUSED
- An Coimisiún Pleanála File Ref.: ABP-305064-19
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted:
- Start Date:
- BCMS Notice:
- View on BCMS Website
Copyright:
Planning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.