Templerainey , Arklow , Co. Wicklow

Jul 02 2024

Application Received

Aug 23 2024

Further Info. Requested

Jan 30 2025

Further Info. Received

Apr 24 2025

Decision

Apr 28 2025

Decision Due

May 27 2025

Granted

May 26 2030

Expiry (if required)
  • Submitted: 02 / 07 / 2024
  • Application Type:
    PERMISSION
  • Application Status:
    APPLICATION FINALISED
  • Council Decision:
    CONDITIONAL (Granted)

Useful Links:

Development Description:

a 10 year permission for the construction of an energy storage facility within a total site area of 0.48 hA to include containerised battery storage modules on concrete support structures, electrical transformer / inverter stations, associated electrical ducting / cabling, security fencing and CCTV security monitoring system, lightning protection poles and ancillary equipment

Nearby Applications:

Appeals / Commencement

No Appeals Found

Decision Appealed:

  • Appeal Submitted:
  • Appeal Status:
  • Appeal Decision:
  • An Coimisiún Pleanála File Ref.:
  • Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.

No Commencement Found

Commencement Information: