Ballyconra Parksgrove and Moatpark , Ballyragget , Co. Kilkenny
Sep 14 2023
Further Info. RequestedJan 05 2024
Further Info. ReceivedFeb 29 2024
Decision DueFeb 29 2024
DecisionApr 02 2024
GrantedAug 11 2032
Expiry (if required)-
Submitted: 21 / 07 / 2023
-
Application Type:
PERMISSION -
Application Status:
APPLICATION FINALISED -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
for the Proposed installation of a network connection and grid connection, and minor amendments to solar farms previously approved under planning application references 17/669 and 22/126. The proposed development will consist of the installation of a 33kV network connection between the solar farms approved under planning application references 17/669 and 22/126 comprising: c. 921m of overhead line and 9 No. wooden poles; onward connection of said approved solar farms to Ballyragget 38kV Substation by installation of a 38kV cable comprising c. 786m of underground cable and c. 395m of overhead line on 5 No. wooden poles; amendments to solar farm approved under planning reference 17/669 comprising removal of substation and replacement with solar panels; amendments to the layout of the substation approved under planning reference 22/126, and all associated site works
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision:
- An Coimisiún Pleanála File Ref.:
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted:
- Start Date:
- BCMS Notice:
- View on BCMS Website
Copyright:
Planning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.