Knockcurraghbola Commons , Upperchurch , Co. Tipperary
Dec 05 2024
DecisionDec 12 2024
Decision DueJan 08 2025
GrantedJan 26 2026
Commencement NoticeFeb 02 2026
Commencement StartedJan 07 2030
Expiry (if required)-
Submitted: 18 / 10 / 2024
-
Application Type:
PERMISSION -
Application Status:
APPLICATION FINALISED -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
the amendments to Upperchurch Windfarm Electrical Substation authorised under An Bord Pleanála Ref. No. Pl.22.243040 and PA92.310171. The amendments consist of a) increase in size of the substation compound yard; b) change to the layout of electrical equipment in the substation compound yard; c) change in size, design and increase in height of the two control buildings and d) ancillary works. The application is accompanied by an Appropriate Assessment Report (stage 1 – screening) and screening for Environmental Impact Assessment (EIA) report
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision:
- An Coimisiún Pleanála File Ref.:
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted: 26 / 01 / 2026
- Start Date: 02 / 02 / 2026
- BCMS Notice: Subscriber Access Required
- View on BCMS Website
Copyright:
Planning Data is published by Department of Housing, Planning and Local Government and is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.