Ionad Pobail agus Fiontraíochta An Rinn , Baile na nGall Beag , An Rinn
Jul 09 2026
DecisionJul 12 2026
Decision Due-
Submitted: 18 / 05 / 2026
-
Application Type:
PERMISSION -
Application Status:
DECISION MADE -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
(a). Single storey entrance building with function space, gallery space, staff kitchen and office space (total gfa: 480 sqm)
(b). Two storey office block (total gfa: 1023 sqm)
(c). Single storey plant/ service block (total gfa: 65 sqm)
The site development works include
- a proposed central courtyard, covered walkways and small outdoor performance space.
- New circulation road and staff parking.
- Primary vehicular access to the site is maintained via the existing main entrance to the site from R674 with proposed upgrading of entrance way.
- Bin Refuse Storage Area and Designated Bicycle Shelter providing for 17 no. spaces.
- New external landscaped areas.
- Extension to existing Playground with new playground facilities and parking.
- All associated site development works including all landscaping and site service works.
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision:
- An Coimisiún Pleanála File Ref.:
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted: