Kerry Technology Park , Dromthacker , Tralee

Dec 10 2025

Application Received

Feb 11 2026

Further Info. Requested

Mar 16 2026

Further Info. Received

Apr 09 2026

Decision

Apr 12 2026

Decision Due

May 13 2026

Granted

May 12 2031

Expiry (if required)
  • Submitted: 10 / 12 / 2025
  • Application Type:
    PERMISSION
  • Application Status:
    N/A
  • Council Decision:
    N/A (Unknown)

Useful Links:

Development Description:

Electricity Supply Board (ESB) intends to apply for permission for development of a 38 kV/MV Gas Insulated Switchgear (GIS) Electrical Substation at this site (1.31ha) at Kerry Technology Park, Dromthacker, Tralee, Co. Kerry. The site is generally bound to the north by the Kerry Technology Park access road (subject to planning permission Ref: 2360295); to the east by the rear of residential properties; to the south by the Knockawaddra Road and the rear of residential and commercial properties along the Knockawaddra Road and to the west by an existing office building and associated car parking area. The proposed development will consist of: • Construction of a substation compound of approximately 2,006m2 gross area enclosed by a 2.6m high stone wall along the northern perimeter of the substation and a 2.6 m high palisade fence around the eastern, southern and western sides of the perimeter of the substation, with the following electrical plant within the substation: • 1 No. prefabricated 38 kV GIS module and foundation (c.31.0m2 and c.5.1 m high); • 1 No. prefabricated MV GIS module and foundation (c.34.0 and c.4.6m high); • 1 No. prefabricated Control Room module and foundation (c.34.0m2 and c.4.6 m high); • 2 No. 38/20 kV 10 MVA transformers and associated bunds (c.45.85m2, c.4.7 m high ea.); • 1 No. House Transformer (c. 7.4 m2 and c. 1.3 m high); and • All associated and ancillary outdoor electrical equipment and other apparatus, including installation of underground cables. • Internal access road within the proposed substation compound. • Site access road and footpath from the existing internal technology park road and footpath. • All associated site development works above and below ground including provision of lighting, boundary fences, landscaping, site services including drainage and all other works.

Nearby Applications:

Appeals / Commencement

No Appeals Found

Decision Appealed:

  • Appeal Submitted:
  • Appeal Status:
  • Appeal Decision:
  • An Coimisiún Pleanála File Ref.:
  • Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.

No Commencement Found