Aughinida Coachford Co. Cork
Dec 18 2024
DecisionDec 19 2024
Decision DueFeb 04 2025
Granted-
Submitted: 05 / 07 / 2024
-
Application Type:
PERMISSION -
Application Status:
APPLICATION FINALISED -
Council Decision:
CONDITIONAL (Granted)
Useful Links:
Development Description:
A 10 year planning permission for a Grid Stability Development. The proposed development will comprise 2 no. control buildings, 120 no. containerised energy storage modules and associated plant and equipment, 20 no. power conversion system units, associated underground electrical ducting and electrical cabling to connect to a transformer/associated 110kV underground grid connection cabling to nearby Clashavoon substation (as previously permitted under Cork County Council reference 23/4541), access tracks, security fencing, landscaping, drainage and all associated ancillary development works and apparatus necessary to facilitate the proposed development. Access to the proposed development will be via an entrance from the L7477 local road to the south (previously permitted under Cork County Council reference 23/4541)
Nearby Applications:
Appeals / Commencement
No Appeals Found
Decision Appealed:
- Appeal Submitted:
- Appeal Status:
- Appeal Decision:
- An Coimisiún Pleanála File Ref.:
- Note: If an appeal has been lodged and information isn't showing then this means An Coimisiún Pleanála hasn't published the data for reuse by PlanningAlerts.ie. You will need to follow up directly on the ACP website. Use the reference number, above, if available.
No Commencement Found
Commencement Information:
- Notice Submitted:
- Start Date:
- BCMS Notice:
- View on BCMS Website
Copyright: